Order of cost estimate
The purpose of an order of cost estimate is to establish affordability of a proposed development for a client.
Methods for preparing order of cost estimates are set out in the New Rules of Measurement:
- NRM 1: Order of cost estimating and cost planning for capital building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works.
NRM1 defines an order of cost estimate as; '...the determination of possible cost of a building(s) early in design stage in relation to the employer’s fundamental requirements. This takes place prior to preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process.'
A wide range of information may be required from the parties to the project to prepare an order of cost estimate:
From the employer:
- Location and availability of site.
- Statement of building use and size.
- Any refurbishment requirements.
- Initial project/design brief.
- Enabling works details.
- Draft programme.
- Site conditions.
- Budget/cash flow constraints.
- Construction procurement options.
- Life span of the proposed building.
From the architect:
- Design study sketches or drawings.
- Schedules of areas.
- Legislative constraints.
- Initial risk register.
Information can also be provided by the services engineer, structural engineer, and other consultants if these have been appointed.
The key constituents of an order of cost estimate are typically:
- Facilitating works.
- Building works.
- Contractor’s preliminaries.
- Contractor’s overheads and profit.
- Construction cost.
- Fees.
- Other development/project costs.
- Risk allowances.
- Inflation.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines an order of cost estimate as: ‘An estimate based on benchmark data for a similar type of project based on a defined brief.’
[edit] Related articles on Designing Buildings
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.